Hi
We’re sorry things didn’t work out, and we never want to see a client inconvenienced.
I’m sure in retrospect you’ll find that your deposit refund was approved on request and a cheque was delivered and cashed within 30 days.
Also, our original work order was for a project start in June/July of 2015, and we were available for construction start at end of August 2015.
(Project milestone dates are below).
To be fair, that’s still a delay and we apologize sincerely.
A previous project had required a significant amount of extra work to complete. On such large projects, safety and quality must come first, and sometimes this means more time on a job than we anticipate.
While it’s not fair to say we refused a refund or put you off for 11 months, we do believe we could have responded to your inquiries more quickly, so we completely understand your request for a refund of your deposit.
We wish you success with your home projects.
Best of luck
Kevin
Project Milestones:
Preliminary contract signed: Sept 6 2014
Construction start scheduled for: June/July 2015
Engineer measurements taken: May 22 2015
Permits issued: June 26 2015
Tall Basements ready to start construction: Aug 31 2015
Client cancellation: Sept 8 2015
Deposit refund cheque cashed Sept 24 2015.