Ready to hire?
Post your job in minutes, browse real reviews and choose who to speak to.Post a jobNeed some tips or advice?
Ask a questionFlooring and tiles
Unfinished basement and flooring
Nabeel 27/10/2026 - 9:36 AM
How long does it take to do level an unfinished basement and install vinyl flooring?
Are you a pro and able to answer this question?
1 Answer
Total Reno & Design
Rating: 5 out of 5
It is a 1 day process to level a floor using self levelling cement and then I would wait a day or two for it to cure. To install LVT flooring in depends on the square footage but again it would be more than 2 -3 days.
Answered27 October 2026
1